On October 19, the field lights and tennis court lights at the old Weddington site on Whitsett Avenue were turned on for testing. Harvard-Westlake said the field lights would go off no later than 8 p.m. and the courts no later than 9 p.m., the same cutoffs that apply once the campus opens. Under the published rules, the public gets the park all day. The tennis courts are public in the morning and at night. Individual swimmers and runners get weekday mornings only, because the afternoon belongs to the school.
Here is a typical school-year weekday under the plan Harvard-Westlake has posted.
| Facility | Public access on a school-year weekday | Who has priority |
|---|---|---|
| 6-acre park, clubhouse, cafe, putting green | 7 a.m. to 9 p.m., every day of the year, free | Open to the public |
| Eight tennis courts | Generally 7 a.m. to 3 p.m. and 6 p.m. to 9 p.m. | Harvard-Westlake when in use |
| Pool, individual lap swimming | 7 a.m. to 9 a.m., September through May | Harvard-Westlake athletes, then community groups |
| Field B and track, individual use | 7 a.m. to noon, September through May | Harvard-Westlake athletes, then community groups |
| Fields, pool, gym for community groups | When not in use by Harvard-Westlake | Harvard-Westlake athletes |
The afternoon belongs to the school
The rest of the schedule follows from one line in the school's FAQ. Harvard-Westlake will generally use the athletic facilities between 1 p.m. and 8 p.m. during the school year, with most use between 3 p.m. and 7 p.m. Compare that with the tennis window and you can see why the public courts close at 3 p.m. and reopen at 6 p.m.
The school puts this generously. It says the public will have the courts "a majority of the time." By the hours listed, that is true. Between 7 a.m. and 9 p.m., a weekday has 11 public hours on the courts against three reserved ones. Those three hours, though, are the late afternoon, which is when anyone with a day job could get to a court before dark.
The pool and the track are tighter. Individual lap swimming runs only from 7 to 9 a.m. on weekdays, and individual use of Field B and the track runs from 7 a.m. to noon. Both are listed for September through May only. The FAQ gives no individual swim or track hours for June through August, and no weekend hours for either. Beyond those windows, the pool is open to pre-approved swim programs and to community groups when athletes aren't using it. Night games end early, too. All outdoor competition stops before 8 p.m., and no football games will be played on site.
So River Park's athletic side is a school facility with public windows cut into it.
The part that stays open all day
The parkland is where the access is unconditional. The six acres and the clubhouse are planned to open every day of the year from 7 a.m. to 9 p.m., free of charge. You will be able to walk in from the Zev Yaroslavsky LA River Greenway or through the main pedestrian and visitor entrance on Whitsett Avenue. The school's list of public features includes the park, plazas, trails, seating, the clubhouse cafe and the putting green.
The cafe has its own history on this site. The FAQ says Café Southwest would close during construction and reopen in the remodeled clubhouse with a new kitchen and more seating. The construction team planned to do that work first, in the hope that the clubhouse and cafe could reopen before the rest of the campus. The FAQ gives no reopening date.
City Planning's project description also calls for landscaped trails that connect to the Greenway, plus an ADA ramp from the Greenway to Coldwater Canyon Avenue. For anyone who already walks the river path, that connection may change daily habits more than any of the sports facilities. It is still a plan on paper, not a route you can use yet.
The baseline is what Weddington Golf & Tennis offered. In July 2023, LAist reported that the nine-hole course cost $12 on weekdays. The course and driving range are gone, and only a putting green replaces them. Light is the other big change. The school says Weddington's driving range lit the site until 11 p.m. every day, for more than 2,000 hours a year. River Park caps outdoor lighting at 600 hours a year, using shielded LED fixtures. Neighbors near the site will get earlier, darker nights.
Why none of it is running yet
Studio City has seen more than one opening date. In April 2026, the Harvard-Westlake Chronicle reported that River Park was expected to open in fall 2026. That target has since moved. The Los Angeles Times reported on July 29, 2026 that construction was nearly done but that the facility still needed inspections and a city Certificate of Occupancy, and that the school was aiming for early 2027. The Chronicle's October 7 report gave the same early-2027 target. Neither source gives an exact opening day.
The school's most recent construction update, dated October 16, shows a site in its final stretch. Crews were installing artificial turf and assembling metal bleachers on Field A. The school warned that the bleacher work might make a metallic sound. The same update scheduled the October 19 light tests.
The work that affects daily driving is outside the fence. The update said sidewalk repair and tree replanting on Whitsett Avenue, with a lane closure, would continue for about two more weeks. Separate sidewalk work on Valley Spring Lane was on the same timeline. Counting from October 16, both should be wrapping up around the end of October. The Chronicle reported on October 7 that the Whitsett closure, which runs from Valley Spring Lane to just before the fire station, was adding traffic. A school dean told the paper her turn took several extra minutes in what she called "snarled" traffic.
The sidewalk work is also permanent. Harvard-Westlake says it is moving the sidewalk farther onto school property, which widens the public right of way. It is also widening the planted strip between sidewalk and street and adding landscaping, including native oaks. According to the July Times report, the 14-foot covered fences along Whitsett were expected to come down soon after that, giving the neighborhood its first real look at the site.
The rules that reach past the fence
Some of River Park's rules are about the streets around it, not the courts. The school plans 386 underground spaces and 17 surface spaces, and every car will enter and leave from Whitsett. Visitors will be told to come in from Ventura Boulevard, turn onto Whitsett, and then turn left into the underground garage. School shuttles have a set route: north on Coldwater Canyon Avenue, right on Moorpark, right on Whitsett. They are barred from residential streets.
The enforcement rule is unusual for a park. The FAQ says on-site security and staff will ask arriving visitors to confirm they haven't parked in the neighborhood. Anyone who has can face penalties up to and including losing permission to use River Park. Students and staff seen driving on residential streets risk losing their privileges too. The school says it will also ban students and employees from parking at River Park on school mornings and taking a shuttle to the Coldwater Canyon campus. For people who live on the side streets north of the site, these are the rules that decide whether a new park also brings new curbside parking pressure.
Not everyone is happy with the project. Traffic, noise, field lighting, the loss of mature trees and the loss of Weddington's public recreation space have all drawn objections. In April 2026, a school spokesperson told the Chronicle that some neighborhood concerns about construction impacts were still unresolved. The school expects some adjustment on its side as well. The Los Angeles Times wrote that the first year will likely be "trial and error" as the school works out how to use the facilities, sorts out traffic patterns and welcomes the public onto grounds open during the school day.
So the timetable in the table above is a plan. It isn't in effect yet. The school's FAQ promises that "many features" will be free, but it does not spell out fees, reservations or how community groups apply for field, pool or gym time. The first published version of those details will show how the public windows work in practice. For now, the morning court hours, the 7-to-9 swim slot and the free daily park hours are the commitments the school has made in writing. For more on the area around the site, see our Studio City neighborhood guide and our field report on what's new along Ventura Boulevard.
A large new neighbor like this changes daily life on the nearby blocks: the morning walk, parking, how dark the evenings get. If you own near Whitsett and want to talk through what River Park's opening year could mean for your home, RSR Real Estate offers a private consultation on your schedule.